| 3/4/04 Status Update Meeting Williams School Project March 5, 2004 |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| News Archives | ||||||||||||||||||||||||||||||||||||||||||||||||||||
| Joseph Gillis Jr | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Local Communities Bridgewater Raynham Easton East Bridgewater West Bridgewater Massachusetts Legislation & Politics USA Legislation & Politics World Education Bridgewater-Raynham Schools Massachusetts USA Archives (past stories) Opinion/Analysis Joseph Gillis Jr. You can do something! |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Above: Current building configuration. The left side is often called the RED side and the right side is often called the WHITE side. Below: New building and site configuration. There is expanded parking on the right side, with dedicated staging and parking for buses on the left. |
||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Home | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Above: Beginning in June 2004, as demolitions begin, this will be the configuration of the site. By the time school begins in the fall of 2004, the left side of the building will be completely closed off. Because some parking area will be lost, a parking area is created on the front left of the site. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Above: Beginning in the fall of 2005, parking will be relocated to a new area. This is to accomodate the many other stepped projects that must be completed prior to opening the left side of the new building. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Above: At about December 2005, the left side of the building will be complete. At this point, the left side will be opened, and the right side of the building will begin it renovations. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Above: This is a model of what the completed project will look like when turned over to the School District. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
| These last 3 images are of the three floors of the school, once the project is complete. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| 1st Floor: 3 station gym (blue), computer lab are (orange), cafetorium (pink), classrooms (green) | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||
| 2nd Floor: Open air above cafetorium (white) and above main entrance. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||